Horse stables

Gan Yashia

Steel

Architecture and Construction: Shaliwood

Completed

Detailed engineering design for a steel structure serving as a horse stable. Approximately 3,000 sqm of customized connection details were carefully designed and coordinated with the execution stages. A total of 115 tons of steel were finalized following the preparation of Shop Drawings (SD), under tight schedule constraints. The project duration was approximately six months, from the design phase through to final delivery.